IREN Data-Center Delays Weigh on Microsoft Capex Ahead of Earnings
Microsoft’s capital spending last quarter was about $5 billion below plan because expected rented data-center capacity was not ready on time. [[fact:fact-rylpmus02]]IREN was identified as one of the suppliers involved, though its specific contribution to the shortfall remains unclear. [[fact:fact-sf7w1udh0]]Microsoft previously agreed to spend $9.7 billion over five years to rent Nvidia servers at IREN’s Childress, Texas, data center. [[fact:fact-b8u61ehfr]]IREN had planned to bring those servers online gradually during 2026 but has faced delays. [[fact:fact-6hloeaoem]]People familiar with the matter said delays at the Childress project led Microsoft to defer spending planned for the quarter ending in September; that specific causal link remains unconfirmed. [[fact:fact-mwttu1476]]IREN shares fell 11.4% in regular trading and another 2.5% overnight. [[fact:fact-hoe13uzzo]]